| R:\Rate Schedules | ||||||||
| 3/20/2009 | 3/20/2010 | |||||||
| Rate Class: | ||||||||
| General Single Phase | 8.4% | Rate Increase | ||||||
| Fixed Charge | $32.90 | $35.00 | per month | |||||
| kWh's | @ | 0.084 | 0.092 | per kWh | ||||
| Seasonal | ||||||||
| Fixed Charge | $394.80 | $420.00 | per year | |||||
| kWh's | @ | 0.084 | 0.092 | per kWh | ||||
| Three Phase | ||||||||
| Fixed Charge | $67.00 | $72.00 | per month | |||||
| First 700 kwhs | @ | 0.084 | 0.092 | per kwh | ||||
| Excess kwhs | @ | |||||||
| Off Peak | ||||||||
| <=50 KVA | @ | $0.044 | $0.048 | per kwh | year round | |||
| summer rate | 0.084 | |||||||
| <=50 KVA short term | 0.067 | 0.074 | per kwh | year round | ||||
| summer rate | 0.084 | |||||||
| >50 KVA | @ | 0.041 | 0.045 | per kwh | year round | |||
| summer rate | 0.084 | |||||||
| ECC Credits >500 kwhs | ($4.00) | ($4.00) | per month | |||||
| ECC Credits >1000 kwhs | ($6.00) | ($6.00) | per month | |||||
| Rental Security Lights (includes tax on energy component only) | ||||||||
| HPS | $8.67 | $9.40 | per month | |||||
| MV | 10.90 | 11.82 | per month | |||||
| MV & Transformer | 16.25 | 17.62 | per month | |||||
| HPS & Transformer | 14.02 | 15.20 | per month | |||||
| 150 watt | 13.86 | 15.02 | per month | |||||
| MV Request | 12.23 | 13.26 | per month | |||||
| Metered Street Lights | ||||||||
| Energy Charge | $0.109 | $0.120 | per kwh | |||||
| Large Power | ||||||||
| Fixed Charge | $74.00 | $79.00 | per month | |||||
| Demand Charge | $9.60 | $10.54 | per KW | |||||
| Energy Charge | ||||||||
| First 100 kwh/KW | 0.063 | 0.069 | per kwh | |||||
| Excess | ||||||||
| Controlled Sawmill | ||||||||
| Guaranteed Max | 0.082 | 0.0943 | per kwh | |||||
| Interruptible Large Power | ||||||||
| Fixed Charge | $1.16 | $1.23 | per KVA | |||||
| Energy | 0.046 | 0.051 | per kwh | |||||
| Demand | $2.00 | $2.20 | per KW | |||||
| Demand Penalty | $60.00 | $93.01 | per KW | |||||
| * A half-cent Temporary Wind Energy Surcharge is in effect from October 20, 2009. It is anticipated | ||||||||
| the economy will improve, the market price of excess wind energy will improve and be sold at rates | ||||||||
| near the generation price, and this surcharge should no longer be needed after June 2011. | ||||||||